The Nepal Water Resource Portal provides a complete picture of Nepal’s water resources and its varied uses. It is a database of all major and minor rivers and river basins along with operational, under construction and under survey hydropower projects on these rivers. In addition, the website includes irrigation projects and groundwater level across the country, giving a spatial representation of Nepal’s water resource and its utilities.


The team working on the portal was inspired by the lack of composite information on how water resources are used or at times even exploited. This portal, therefore, provides a tool to analyze water resources and the development of a region. It uses GIS to locate the infrastructure projects on each river, within the administrative boundaries along with the salient features of those projects, bringing to light the developmental trajectory of our rivers.

River with Hydropower Projects

mai khola

1

Projects

Nyam Nyam Khola

Nuwakot,Rasuwa

  • Nyam Nyam Hydropower Project
mai khola

1

Projects

Saiti Khola

Dailekh,Kaski

  • Saiti Khola Small Hydropower Project
mai khola

1

Projects

Rele Khola

Myagdi

  • Rele Khola Hydropower Project
mai khola

1

Projects

Gaddi Gad

Achham,Doti

  • Upper Gaddi Gad Hydropower Project
mai khola

1

Projects

Taman Khola

Baglung

  • Taman Khola Hydropower Project
mai khola

1

Projects

Garchyang Khola

Kaski

  • Garchyang Khola Hydropower Project
mai khola

1

Projects

Jadari Gad

Bajhang

  • Jadari Gad Hydropower Project
mai khola

1

Projects

Jhankre Khola

Nuwakot

  • Jhankre Mini Hydropower Project
mai khola

1

Projects

Thame Khola

Solukhumbu

  • Thame Small Hydropower Project
mai khola

1

Projects

Giri Khola

Jumla

  • Giri Khola Hydropower Project
mai khola

1

Projects

Dhangsi Khola

Rolpa

  • Dhansi Khola Mini Hydropower Project
mai khola

1

Projects

Gumdi Khola

Sindhupalchok

  • Gelun Khola Hydropower Project

Hydropower Projects

mai khola

Mugu Khola HEP

Kimari,Dolphu,Mugu,Pulu (Mugu)

  • Issue Date: 2019-01-21
  • Installed Capacity : 57 MW
  • Phase : Survey License Approved
  • Type : Run-of-the-river
mai khola

Chuwa Khola HEP

Bargaun,Kharpunath,Thechaya (Humla)

  • Issue Date: 2019-01-18
  • Installed Capacity : 70 MW
  • Phase : Survey License Approved
  • Type : Run-of-the-river
mai khola

Tarap Khola HEP

Mukot,Lawan (Dolpa)

  • Issue Date: 2018-12-25
  • Installed Capacity : 50 MW
  • Phase : Survey License Approved
  • Type : Run-of-the-river
mai khola

Bhotekoshi Khola HEP

Chilime,Briddhim,Goljung (Rasuwa)

  • Issue Date: 2018-05-24
  • Installed Capacity : 33.5 MW
  • Phase : Survey License Approved
  • Type : Run-of-the-river
mai khola

Ikhuwa Khola HEP

Pathibhara,Pawakhola (Sankhuwasabha)

  • Issue Date: 2018-04-20
  • Installed Capacity : 30 MW
  • Phase : Survey License Approved
  • Type : Run-of-the-river
mai khola

Upper Barunkhola HEP

Makalu (Sankhuwasabha)

  • Issue Date: 2018-04-08
  • Installed Capacity : 55 MW
  • Phase : Survey License Approved
  • Type : Run-of-the-river
mai khola

Chunchet Syar Khola HEP

Sirdibas,Chunchet,Bihi (Gorkha)

  • Issue Date: 2018-04-18
  • Installed Capacity : 60 MW
  • Phase : Survey License Approved
  • Type : Run-of-the-river
mai khola

Karuwa Seti HEP

Machhapuchchhre,Sardikhola (Kaski)

  • Issue Date: 2018-04-08
  • Installed Capacity : 32 MW
  • Phase : Under Construction
  • Type : Run-of-the-river
mai khola

Tom Dogar HEP ( Budhi gandaki)

Bihi (Gorkha)

  • Issue Date: 2018-02-25
  • Installed Capacity : 43.52 MW
  • Phase : Survey License Approved
  • Type : Run-of-the-river
mai khola

Dudhkoshi V HEP

Ravi Bhawan, Kathmandu

  • Application Date: 2020-09-20
  • Installed Capacity : 102 MW
  • Phase : Application for Survey License
mai khola

Manaslu HEP

kathmandu-16, Kathmandu

  • Application Date: 2020-08-31
  • Installed Capacity : 19 MW
  • Phase : Application for Survey License
  • Type : Run-of-River
mai khola

Sangu Khola

Kalingchok, Khupachagu (Dolakha)

  • Issue Date: 2020-01-15
  • Installed Capacity : 5 MW
  • Phase : Under Construction
  • Type : Run-of-River