dam side

About Nepal Water Resource Portal

The Nepal Water Resource Portal provides a complete picture of Nepal’s water resources and its varied uses. It is a database of all major and minor rivers and river basins along with operational, under construction and under survey hydropower projects on these rivers. In addition, the website includes irrigation projects and groundwater level across the country, giving a spatial representation of Nepal’s water resource and its utilities.


The team working on the portal was inspired by the lack of composite information on how water resources are used or at times even exploited. This portal, therefore, provides a tool to analyze water resources and the development of a region. It uses GIS to locate the infrastructure projects on each river, within the administrative boundaries along with the salient features of those projects, bringing to light the developmental trajectory of our rivers.

River with Hydropower Projects

mai khola

4

Projects

Mewa Khola

Ilam,Panchthar,Sarlahi,Taplejung

  • Mewa Khola Hydropower project
  • Mewa khola HPP
  • Middle Mewa HPP
  • Tamor Mewa Hydropower Project
mai khola

4

Projects

Irkhuwa Khola

Bhojpur

  • Irkhuwa Khola-B Hydropower Project
  • Irkhuwa Khola Ka HPP
  • Upper Irkhuwa Hydropower Project
  • Lower Irkhuwa Khola Hydropower Project
mai khola

4

Projects

Arun Khola

Dhading

  • Lower Arun Hydroelectric Project
  • Upper Arun Hydroelectric Project
  • Arun Khola 2 HEP
  • Arun 3 Hydropower Project
mai khola

4

Projects

Budhi Gandaki River

Dhading,Gorkha

  • Budhigandaki Ka Hydropower Project
  • Tom Dogar HEP ( Budhi gandaki)
  • Budhigandaki Ka Hydroelectric Project
  • Budhi Gandaki HEP
mai khola

4

Projects

Chepe Khola

Gorkha,Ilam,Lamjung,Tanahu

  • Super Chepe HEP
  • Chepe Khola HEP
  • Chepe Khola Small HEP
  • Dudhpokhari Chepe HEP
mai khola

4

Projects

Hongu Khola

Solukhumbu

  • Middle Hongu Khola B HPP
  • Middle Hongukhola A Hydropower Project
  • Hongu Khola I HEP
  • Hongu Khola HEP
mai khola

3

Projects

Sunkoshi Nadi

Bhojpur,Dhankuta,Kabhrepalanchok,Khotang,Okhaldhunga,Ramechhap,Sindhuli,Sindhupalchok,Udayapur

  • Sunkoshi Hydropower Station
  • Sunkoshi Small Hydropower Project
  • Middle Sunkoshi Hydropower Project
mai khola

3

Projects

Chamaliya Nadi

Baitadi,Darchula

  • Chameliya (Chhetigad) Hydropower Project
  • Chameliya Khola Hydropower Project
  • Upper Chameliya Hydropower Project
mai khola

3

Projects

Daram Khola

Baglung,Gulmi

  • Daram khola A Hydroelectric Project
  • Daram Khola Hydroelectric Project
  • Middle Daram Khola-B Hydropower Project
mai khola

3

Projects

Jogmai Khola

Ilam

  • Jogmai Khola Small Hydroelectric Project
  • Lower jogmai Khola
  • Jogmai Cascade
mai khola

3

Projects

Bagmati Nadi

Kabhrepalanchok,Kathmandu,Lalitpur,Makawanpur,Rautahat,Sarlahi,Sindhuli

  • Bagmati Nadi Hydropower Project
  • Tallo Bagmati Small HPP
  • Malta Bagmati Small Hydro Power Project
mai khola

3

Projects

Sanjen Khola

Rasuwa

  • Sanjen Khola Hydropower Project
  • Sanjen Hydropower Project
  • Upper Sanjen Hydropower Project

Hydropower Projects

mai khola

Mugu Khola HEP

Kimari,Dolphu,Mugu,Pulu (Mugu)

  • Issue Date: 2019-01-21
  • Installed Capacity : 57 MW
  • Phase : Survey License Approved
  • Type : Run-of-the-river
mai khola

Chuwa Khola HEP

Bargaun,Kharpunath,Thechaya (Humla)

  • Issue Date: 2019-01-18
  • Installed Capacity : 70 MW
  • Phase : Survey License Approved
  • Type : Run-of-the-river
mai khola

Tarap Khola HEP

Mukot,Lawan (Dolpa)

  • Issue Date: 2018-12-25
  • Installed Capacity : 50 MW
  • Phase : Survey License Approved
  • Type : Run-of-the-river
mai khola

Bhotekoshi Khola HEP

Chilime,Briddhim,Goljung (Rasuwa)

  • Issue Date: 2018-05-24
  • Installed Capacity : 33.5 MW
  • Phase : Survey License Approved
  • Type : Run-of-the-river
mai khola

Ikhuwa Khola HEP

Pathibhara,Pawakhola (Sankhuwasabha)

  • Issue Date: 2018-04-20
  • Installed Capacity : 30 MW
  • Phase : Survey License Approved
  • Type : Run-of-the-river
mai khola

Upper Barunkhola HEP

Makalu (Sankhuwasabha)

  • Issue Date: 2018-04-08
  • Installed Capacity : 55 MW
  • Phase : Survey License Approved
  • Type : Run-of-the-river
mai khola

Chunchet Syar Khola HEP

Sirdibas,Chunchet,Bihi (Gorkha)

  • Issue Date: 2018-04-18
  • Installed Capacity : 60 MW
  • Phase : Survey License Approved
  • Type : Run-of-the-river
mai khola

Karuwa Seti HEP

Machhapuchchhre,Sardikhola (Kaski)

  • Issue Date: 2018-04-08
  • Installed Capacity : 32 MW
  • Phase : Under Construction
  • Type : Run-of-the-river
mai khola

Tom Dogar HEP ( Budhi gandaki)

Bihi (Gorkha)

  • Issue Date: 2018-02-25
  • Installed Capacity : 43.52 MW
  • Phase : Survey License Approved
  • Type : Run-of-the-river
mai khola

Dudhkoshi V HEP

Ravi Bhawan, Kathmandu

  • Application Date: 2020-09-20
  • Installed Capacity : 102 MW
  • Phase : Application for Survey License
mai khola

Manaslu HEP

kathmandu-16, Kathmandu

  • Application Date: 2020-08-31
  • Installed Capacity : 19 MW
  • Phase : Application for Survey License
  • Type : Run-of-River
mai khola

Sangu Khola

Kalingchok, Khupachagu (Dolakha)

  • Issue Date: 2020-01-15
  • Installed Capacity : 5 MW
  • Phase : Under Construction
  • Type : Run-of-River