dam side

About Nepal Water Resource Portal

The Nepal Water Resource Portal provides a complete picture of Nepal’s water resources and its varied uses. It is a database of all major and minor rivers and river basins along with operational, under construction and under survey hydropower projects on these rivers. In addition, the website includes irrigation projects and groundwater level across the country, giving a spatial representation of Nepal’s water resource and its utilities.


The team working on the portal was inspired by the lack of composite information on how water resources are used or at times even exploited. This portal, therefore, provides a tool to analyze water resources and the development of a region. It uses GIS to locate the infrastructure projects on each river, within the administrative boundaries along with the salient features of those projects, bringing to light the developmental trajectory of our rivers.

River with Hydropower Projects

mai khola

2

Projects

Phawa Khola

Dhankuta,Panchthar,Taplejung

  • Upper Phawa Hydropower Project
  • Phawa khola Hydropower Project
mai khola

2

Projects

Sardi Khola

Kaski

  • Sardikhola Hydropower Project
  • Upper Sardi Hydropower Project
mai khola

2

Projects

Tatopani Khola

Myagdi

  • Tatopani Small Hydropower Project
  • Ilep Tatopani Khola HPP
mai khola

2

Projects

Tinau Nadi

Palpa,Rupandehi

  • Tinau Hydropower
  • Tinau Khola Hydropower Project
mai khola

2

Projects

Jumdi Khola

Gulmi

  • Jumdi Khola Small Hydropower Project
  • Upper Jumdi Khola Hydropower Project
mai khola

2

Projects

Khare Khola

Achham,Bajhang,Bardiya,Dolakha,Jumla,Nuwakot,Rolpa,Rukum_E,Surkhet

  • Khare Hydropower Project
  • Lower Khare Hydropower Project
mai khola

2

Projects

Lohore Khola

Achham,Dailekh

  • Lohare Khola Hydropower Project
  • Upper Lohore Small Hydropower Peoject
mai khola

2

Projects

Rudi Khola

Bajura,Kaski,Lamjung

  • Rudi A Hydropower Project
  • Rudi Khola-B Hydropower Project
mai khola

2

Projects

Ghalemdi Khola

Myagdi

  • Super Ghalemdi HPP
  • Ghalemdi Khola Hydropower Project
mai khola

2

Projects

Rupse Khola

Bhojpur,Dhading,Myagdi,Udayapur

  • Rupse Khola Hydropower Project
  • Lower Rupse Khola HEP
mai khola

2

Projects

Suri Khola

Dolakha,Kapilbastu

  • Suri Khola Hydropower Project
  • Upper Suri Khola Hydropower Project
mai khola

2

Projects

Kalanga Nadi

Bajhang,Doti

  • Upper Kalangad Hydropower Project
  • Kalanga Hydropower Project

Hydropower Projects

mai khola

Bhairabkund Small Hydropower Project

Sindhupalchok

  • Commercial Operation Date : 2014-05-16
  • Installed Capacity : 3 MW
  • Phase : Live
  • Type : Run-of-River
mai khola

Mailung Khola Hydropower Project

Rasuwa

  • Commercial Operation Date : 2014-03-17
  • Installed Capacity : 5 MW
  • Phase : Live
  • Type : Run-of-River
mai khola

Molun Khola Small Hydropower Project

Okhaldhunga

  • Commercial Operation Date : 2018-02-24
  • Installed Capacity : 7 MW
  • Phase : Live
  • Type : Run-of-River
mai khola

Dhad Khola Small Hydropower Project

Dharampani, Tanahun

  • Issue Date: 2010-03-10
  • Installed Capacity : 2.720 MW
  • Phase : Application for Generation License
  • Type : Run-of-River
mai khola

Super Hewa Hydropower Project

Jaljala,Siddhapokhari (Sankhuwasabha)

  • Issue Date: 2010-08-29
  • Installed Capacity : 5.0 MW
  • Phase : Under Construction
mai khola

Upper Marsyangdi- 2 Hydropower Project

Ghermu,Taghring (Lamjung)

  • Issue Date: 2011-09-12
  • Installed Capacity : 600 MW
  • Phase : Application for Generation License
mai khola

Upper Rahughat Hydropower Project

Chimkhola, Myagdi

  • Issue Date: 2013-06-17
  • Installed Capacity : 48.5 MW
  • Phase : Under Construction
mai khola

Jhyaku Khola Hydropower Project

Jhyaku, Dolakha

  • Issue Date: 2018-09-20
  • Installed Capacity : 5.243 MW
  • Phase : Under Construction
mai khola

Dudhkoshi-2 (Jaleswar) Hydropower Project

Deusa, Solukhumbhu

  • Issue Date: 2018-09-20
  • Installed Capacity : 70 MW
  • Phase : Under Construction
mai khola

Upper Trishuli-2 Hydropower Project

Haku, Rasuwa

The proposed Upper Trishuli-2 Hydroelectric project of 102 MW capacity is situated 127 km north of Kathmandu, the capital city of Nepal, on the Trishuli River about 950 m downstream of Chilime Powerhouse (22 MW) in the Rasuwa District of Bagmati zone in the Central Development Region of Nepal. Proposed project is a Run-of-River (RoR) scheme aimed at utilizing the design discharge of 110 m3/s to generate average annual hydro-based electric energy of 593 GWh. The catchment area at the proposed intake site is 4064 km2 and the rated head is 99.6 m.
  • Issue Date: 2018-09-20
  • Installed Capacity : 102.0 MW
  • Phase : Under Construction
mai khola

Middle Trishuli Ganga Nadi Hydropower Project

Gerkhu, Nuwakot

  • Issue Date: 2018-09-20
  • Installed Capacity : 65 MW
  • Phase : Application for Generation License
  • Type : Run-of-River
mai khola

Gandigad Small Hydropower Project

Kolpetara, Baitadi

  • Issue Date: 2018-09-20
  • Installed Capacity : 1 MW
  • Phase : Under Construction