The Nepal Water Resource Portal provides a complete picture of Nepal’s water resources and its varied uses. It is a database of all major and minor rivers and river basins along with operational, under construction and under survey hydropower projects on these rivers. In addition, the website includes irrigation projects and groundwater level across the country, giving a spatial representation of Nepal’s water resource and its utilities.


The team working on the portal was inspired by the lack of composite information on how water resources are used or at times even exploited. This portal, therefore, provides a tool to analyze water resources and the development of a region. It uses GIS to locate the infrastructure projects on each river, within the administrative boundaries along with the salient features of those projects, bringing to light the developmental trajectory of our rivers.

Under Construction Hydropower Projects

mai khola

Dordi-1 Hydropower Project

Chiti,Bansar,Dhodeni,Faleni (Lamjung)

The project is located in Dordi Gaupalika-6, Lamjung. Its registered office is located at Kathmandu -11, Bluestar Complex, Tripureshor.
  • Issue Date: 2013-01-25
  • Installed Capacity : 12 MW
  • Phase : Under Construction
mai khola

Nyadi Khola Hydropower Project

Bahundada,Bhulbhule (Lamjung)

  • Issue Date: 2013-02-14
  • Installed Capacity : 30 MW
  • Phase : Under Construction
  • Type : 30
mai khola

Upper Jumdi Khola Hydropower Project

Juhang,Bharse,Hasara (Gulmi)

  • Issue Date: 2013-02-26
  • Installed Capacity : 0.995 MW
  • Phase : Under Construction
mai khola

Lower Tadi Hydropower Project

Balkumari,Samundratar,Sundaradevi,Thaprek (Nuwakot)

  • Issue Date: 2013-04-08
  • Installed Capacity : 4.993 MW
  • Phase : Under Construction
mai khola

Khorunga Khola Hydropower Project

Ambung,Oyabjung (Terhathum)

  • Issue Date: 2013-04-10
  • Installed Capacity : 4.8 MW
  • Phase : Under Construction
mai khola

Gelun Khola Hydropower Project

Baramchi,Hagam,Jalbire (Sindhupalchok)

  • Issue Date: 2013-05-20
  • Installed Capacity : 3.2 MW
  • Phase : Under Construction
mai khola

Khani Khola (Dolakha) Hydropower Project

Marbu,Khare (Dolakha)

  • Issue Date: 2013-05-24
  • Installed Capacity : 30 MW
  • Phase : Under Construction
mai khola

Middle Modi

Deupurkot,Tilahar (Parbat)

Middle Modi Hydroelectric Project (15 MW) Middle Modi Hydroelectric Project (MMHP) is located about 40 km north-west of Pokhara in Kaski and Parbat Districts, Gandaki Zone of Western Development. The project lies in the Bhuktangle, Deupur and Tilhar VDCs of Parbat District and Salyan and Lumle VDCs of Kaski District. The headworks is located at Birethanti village. At present there is about 1.5km long earthen road access to the headworks area from Nayapul bazaar which is the nearest point with all year road access along the Pokhara – Baglung highway. The powerhouse lies opposite to the Pokhara – Baglung highway at the right bank of the Modi with waterway alignment located at the right bank of Modi Khola.
  • Issue Date: 2013-06-25
  • Installed Capacity : 15.1 MW
  • Phase : Under Construction
  • Type : Run of River
mai khola

Dhunge - Jiri Hydropower Project

Jiri (Dolakha)

  • Issue Date: 2013-07-08
  • Installed Capacity : 0.6 MW
  • Phase : Under Construction
mai khola

Middle Midim Hydropower Project

,Gilung,Karapu,Maling,Nalma (Lamjung)

  • Issue Date: 2013-07-25
  • Installed Capacity : 3.1 MW
  • Phase : Under Construction
mai khola

Upper Trishuli 3B Hydropower Project

Manakamana (Nuwakot)

  • Issue Date: 2013-08-11
  • Installed Capacity : 37 MW
  • Phase : Under Construction
mai khola

Parajuli Khola-1 Hydropower Project

Awal Parajul (Dailekh)

  • Issue Date: 2013-08-19
  • Installed Capacity : 2.15 MW
  • Phase : Under Construction