3

Projects

Hydropower Projects Constructed:
Sanima Hydropower Pvt.Ltd

2.6MW

Installed capacity

Sunkoshi Small Hydropower Project

Sunkoshi Nadi
Sindhupalchok
Commercial Operation Date : 2005-03-24
Installed Capacity : 2.6 MW
Phase : Live
View On Map

56MW

Installed capacity

Jum Khola Hydropower Project

Sunkoshi Nadi , Jum Khola
Lamabagar (Dolakha)
Issue Date: 2015-12-24
Installed Capacity : 56 MW
Phase : Survey License Approved
View On Map

7.5MW

Installed capacity

Upper Mailung B HEP

Sunkoshi Nadi , Jum Khola , Mailung Khola
Dandagoun,Haku (Rasuwa)
Issue Date: 2016-11-18
Installed Capacity : 7.5 MW
Phase : Survey License Approved
View On Map
check-mark

Application for Survey License

0
check-mark

Survey License Approved

2
check-mark

Application for Generation License

0
check-mark

Under Construction

0
check-mark

Live

1