Application for Survey License
Survey License Approved
Application for Generation License
Under Construction
Live
GKHPP is run-off-the river (ROR) type hydropower project with an installed capacity of 14 MW (2 X 7MW) .The project has design discharge of 3.46 m3/s and net head of 480.33m that generates 78.498 GWh of energy annually. The proposed Headworks site lies at an elevation of 1645.0 m of GharKhola and the Powerhouse is located at an elevation of 1185 m, 300 m downstream of the confluence of Ghar Khola with Kaligandaki River. Project consists of about 3030 m of tunnel (Finished Dimension (2.4 m x 2.6 m). There is 57 m long Surge Pipe (Internal dia. 2.2m) followed by 1.2 m dia. 1281m long Penstock Pipe.