Lower Modi-2 Hydropower Project (10.5 MW) is being developed as the cascade project of the upstream Lower Modi-1 Hydropower project. The project is in its design phase. The energy generated from the project will be evacuated to the national grid by 3 km, 132 kv transmission line to existing Lower Modi-1 switchyard and then on common system to NEA Modi Substation at Dimuwa, Parbat. The connection agreement is concluded with NEA, and the PPA is in process. The Detailed Project Report (DPR) of the project is near to completion. The construction of the project is estimated to begin from early 2016.

Salient Features

Hydrology ( Intake )

Catchment Area 645 km2
Design Discharge 26.0 m3/sec
Maximum Gross Head 49.40 m
check-mark

Application for Survey License

check-mark

Survey License Approved

check-mark

Application for Generation License

check-mark

Under Construction

check-mark

Live