
Application for Survey License

Survey License Approved

Application for Generation License

Under Construction

Live
The proposed Upper Trishuli-2 Hydroelectric project of 102 MW capacity is situated 127 km north of Kathmandu, the capital city of Nepal, on the Trishuli River about 950 m downstream of Chilime Powerhouse (22 MW) in the Rasuwa District of Bagmati zone in the Central Development Region of Nepal. Proposed project is a Run-of-River (RoR) scheme aimed at utilizing the design discharge of 110 m3/s to generate average annual hydro-based electric energy of 593 GWh. The catchment area at the proposed intake site is 4064 km2 and the rated head is 99.6 m.
Catchment Area | 4064 km2 |
---|---|
Design Discharge | 110 m3/s |
Penstock- Length | 4 m |
---|
Type | Francis |
---|---|
Number of Units | 2 |
Rated Output | 51 MW |
Application for Survey License
Survey License Approved
Application for Generation License
Under Construction
Live