3

Projects

Hydropower Projects Constructed:
Chilime Hydropower Company Limited

130MW

Installed capacity

Budhigandaki Ka Hydropower Project

Budhi Gandaki River
Uiya (Gorkha)
Application Date: 2018-03-28
Installed Capacity : 130 MW
Phase : Application for Survey License
View On Map

60MW

Installed capacity

Chunchet Syar Khola HEP

Budhi Gandaki River , Syar Khola
Sirdibas,Chunchet,Bihi (Gorkha)
Issue Date: 2018-04-18
Installed Capacity : 60 MW
Phase : Survey License Approved
View On Map

22MW

Installed capacity

Chilime Hydropower Plant

Budhi Gandaki River , Syar Khola , Chilime Khola
Chilime, Rasuwa
Commercial Operation Date : 2003-08-25
Installed Capacity : 22 MW
Phase : Live
View On Map
check-mark

Application for Survey License

1
check-mark

Survey License Approved

1
check-mark

Application for Generation License

0
check-mark

Under Construction

0
check-mark

Live

1